6. Screed to top of floor box surface. Hand troweling
recommended near box edges.
7. Remove mudcap.
NOTE: Mud Cap is NOT a load bearing surface and additional
material should be placed into the mud cap to bear
the appropriate traffic loads.
CAUTION: Do not dislodge or shift box with jobsite traffic or
concrete vibrations.
9. If tunnels are to be used, remove tunnel by removing (2)
#8-32 screws. Remove the spacer plate located behind
the tunnel and reinstall the tunnel.
8. Determine required location and mount divider,
Cat No. CCBBS-DIV on device bracket.
5. Reinstall mudcap.
10. Locate and pull wires and cables.
Polished Concrete
Floor Spacer: Spacer
must be installed prior
to pouring concrete.